Activity plan of the project

Coordinator country is responsible for all administrative coordination.Partners in the project are obliged to comply with the specified protocol requirements, fulfill their duties, report to the coordinator at specified intervals and participate inproject meetings.Each partner will fit into work schedule. Each partner is obliged to fulfill all the activities specified in the working calendar. The project management and implementation budget includes transnational meetings, sharing day activities,cultural tasks and reporting tools.

The tasks that will be met from the budget of project management and implementation are summarized below:

September 2017:
A1- Establishment of communication network of the project
A2- Preparation of project Logo
A3- Visibility in the rules of the project promotion activities
A4- Project presentation showing the arrangement of school boards
A5- Preparing the pre-evaluation survey

October 2017:
M1- 1st meeting (Turkey)
A6- Forming the web page platform for experience and knowledge sharing.
A7- Creating a Facebook page for sharing all the process of the project.
A8- “Sharing Box” in Turkey.

November 2017:
A9 – Classroom implementation and introduction of exploring innovative practices of European dimension.
A10- “Sharing Day” activities.

December 2017:
A11- Holding the photo contest called “Diagnose your culture and introduce”.
A10- “Sharing Day” activities.

January 2018:
A12- Making research about famous artists of the partnership countries, and preparing documents.
A10- “Sharing Day” activities.

March 2018:
A14- Classroom implementation and introduction of exploring innovative practices of the European dimension.
A10 – “Sharing Day” activities.

April 2018:
A15 – Evaluating the web page for sharing and exchanging experiences and knowledge.
A10- “Sharing Day” activities.

May 2018:
A16-Evaluation of “Sharing Day” activities

June 2018:
M2- 2nd meeting (Portugal)
A17- Introducing previous sharing activities as a video power point presentation
A18- Updating the content of the web page for sharing and exchanging experiences and knowledge.
A10 – Realization of “Sharing Day” activities.
A8- ”Share Box” in Portugal.

July-August 2018:
A19- Writing the progress report.

September 2018:
A20 – Starting the procedures to make a simple and informative video about cultural elements and exchange of teaching practices and professional skills,and adding sign language.
A10- ”Sharing Day”activities.

October – November 2018:
A21 – Making investigation of memory and intelligence improving games and specifically playing and recording games of the partner countries
A22- Completing “Intercultural Relations and Cultural Art Elements” brochure and making it ready for printing.
A10- “Sharing Day” activities.

December 2018:
A23- Completing project’s introduction video.
A10- “Sharing Day” activities.

January 2019:
A24- Adding sign language and subtitles in languages of partner countries to project’s introduction video.
A10-“Sharing Day” activities.

February 2019:
C1 – LTT activities; cooking, serving and tasting the cuisine of the participant countries by related stakeholders and general public, in Italy
A8- Sharing Box in Italy

March 2019:
A25 -Carrying out cultural dance, theater and music activities performed by students.
A10-“Sharing Day” activities.
A26- Learning with C.A.K.E Preparing a book of growth with CAKE

April 2019:
A26- Disseminating and sharing of the project website.
A27- Finalizing project evaluation surveys.
A10 -“Sharing Day” activities.

May 2019:
A28- Making local and national dissemination activities.
A29- Disseminating the school activities.
A30 -Displaying introduction video.
A10 -”Sharing Day” activities.
A26- Learning with C.A.K.E Preparing a book of growth with CAKE

June 2019:
M3- Final meeting (Turkey)
A31- Making overall evaluation of the project and preparing a conclusive report in collaboration with the partners.
A26- Learning with C.A.K.E Preparing a book of growth with CAKE

July-August 2019:
A32- Writing the final project report.